CPM Duration Formula:
From: | To: |
The Critical Path Method (CPM) is a project management technique used to determine the longest path of dependent tasks and calculate the minimum project duration. It helps identify critical tasks that directly impact the project timeline.
The calculator uses the CPM duration formula:
Where:
Explanation: The CPM duration represents the total time required to complete all critical path tasks sequentially, determining the minimum project completion time.
Details: Accurate CPM calculation is crucial for project planning, scheduling, resource allocation, and identifying tasks that can delay the entire project if not completed on time.
Tips: Enter the sum of critical path tasks duration in days. The value must be valid (greater than 0).
Q1: What is the critical path in project management?
A: The critical path is the longest sequence of tasks that determines the minimum project duration. Any delay in critical path tasks will delay the entire project.
Q2: How is CPM different from PERT?
A: CPM uses deterministic time estimates while PERT uses probabilistic estimates. CPM focuses on time-cost trade-offs while PERT handles uncertainty in task durations.
Q3: What are float and slack in CPM?
A: Float or slack is the amount of time a task can be delayed without affecting the project completion date. Critical path tasks have zero float.
Q4: Can critical path change during a project?
A: Yes, the critical path can change as task durations are updated or as dependencies change during project execution.
Q5: What software tools support CPM analysis?
A: Popular tools include Microsoft Project, Primavera P6, Smartsheet, and various online project management platforms that support critical path analysis.